Project Lifecycle Management Essentials

Question No: 51

Which term means executing the systematic quality activities to determine if the quality processes are being followed and whether they are satisfying the project quality needs?

  1. Quality Planning

  2. Quality Control

  3. Quality Assurance

  4. Process Improvement

Answer: B

Question No: 52

Which is the true about OUM Manage?

  1. If the client is not involved in the planning process, the project should move ahead without approval.

  2. If the client is involved in the planning process, the project should move ahead without approval.

  3. The plans are only produced by the project team.

  4. If the client is not interested in helping to produce the necessary plans, then at a minimum, they are made aware of the plans and must sign-off on them.

  5. If the client is not interested to produce necessary plans, the project manager must limit the scope of work to only Inception.

Answer: D

Question No: 53

Which is the type of closure described as the mechanical an analytical step associated with the closure of a project or phase?

  1. Contractual

  2. Typical

  3. Intra-business

  4. Conventional

Answer: A

Question No: 54

Which statement is true about the Custom Development Sub-Flow of the OUM Implement Core Workflow?

  1. It should be included in every OUM project plan.

  2. It should be included in the workplan when there are configuration tasks identified.

  3. It should be included in the workplan when gaps are identified while mapping requirements.

  4. It should only be included on SOA projects.

Answer: D Explanation: Note:

*The first step is to start from a core set of tasks. We recommend that you consider using the OUM Implement Core Workflow for this purpose along with an OUM view that best matches the needs of your project. Remember, though, that the views tend to be a superset of tasks related to a particular solution, discipline, or technology. Therefore, the core workflow and views should be used together to achieve the right balance for your project.

Question No: 55

An is a distinct set of activities conducted according to a devoted plan and evaluation criteria that results in a release, either internal or external.

  1. Iteration

  2. Internal

  3. Increment

  4. Approach

  5. Implement

Answer: A

Explanation: Iterative and Incremental

OUM recognizes the advantages of an iterative and incremental approach to development and

deployment of information systems. Any of the tasks within OUM may be iterated. Whether or

not to iterate, as well as the number of iterations, varies. Tasks may be iterated to increase quality of the work products to a desired level, to add sufficient level of detail, or to refine and

expand the work products on the basis of user feedback

Question No: 56

Inthe following diagram, wherewould thearrowfrom the extension usecase, Get AdditionalCollateral,begin and end?

Ensurepass 2018 PDF and VCE

  1. Begin at Get Additional Collateral and end at Review Loan for approval

  2. Begin at Review Loan for Approval and end at get Additional Collateral

  3. Begin at the Loan approver and end at get Additional Collateral

  4. Begin at get Additional Collateral and end at CPS actor

Answer: C

Question No: 57

The OUM Manage Focus Area is aligned with what project management organization?

  1. Project Management Institute (PMI)

  2. Project Management Organization

  3. Project Managers of the World

  4. NationalInstitute of Project Managers

  5. International Institute of Business Analysis (IIBA)

Answer: A

Question No: 58

Selectfourobjectives of the OUM Manage Project Start UP phase.

  1. Manage the project resources to deliver on time and budget.

  2. Understand the client’s objectives and expectations and validate project scope.

  3. Close out the contractual agreement.

  4. Baseline in Project Workplan, Finance Plan, and staffing needs.

  5. Obtain a client reference.

  6. Agree with the client on project approach and document it in the Project Management Plan.

  7. Establish the project infrastructure.

Answer: B,C,D,F Explanation: Note:

*The Project Start Up phase precedes the Inception phase. Project startup is where all of the projectplanning activities take place and where policies, procedures, and strategies are defined for each of theprocesses, which govern the conduct of the engagement.

Question No: 59

Using the 2 x 2Urgency/ImportanceMatrix below, select the use case withhighestpriority.

Ensurepass 2018 PDF and VCE

  1. UC2

  2. UC4

  3. UC6

  4. UC8

  5. UC10

Answer: E

Question No: 60

Identify the three functions that OUM Manage performs.

  1. provides training on project management basics

  2. Facilitates, supports, and standardizes the program or project management process.

  3. Documents standard operating procedures

  4. Provides a standard framework and reference guide

  5. Supports both projects and programs

  6. Supports application projects only

Answer: B,D,E Explanation:

Note:

*The Manage focus area is organized into 13 processes: Bid Transition

Scope Management Financial Management Work Management Risk Management

Issue and Problem Management Staff Management Communication Management Quality Management Configuration Management Infrastructure Management Procurement Management

Organizational Change Management

Collectively, these processes form a comprehensive set of tasks required to manage Oracle-based

development and implementation projects. Every project includes most, if not all, of these processes,

whether they are the responsibility of a consulting organization, a client organization, or a third party.

100% Ensurepass Free Download!
Download Free Demo:1z0-466 Demo PDF
100% Ensurepass Free Guaranteed!
1z0-466 Dumps

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No